Soru 1
What is an uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives?
Soru 2
Project risks are divided into two categories. Which of the following states these categories correctly?
Soru 3
What is necessary in order to effectively monitor and control risks in a project?
Soru 4
Which risk identification technique can help you to see the many risks associated with the project in a short time with the participation of people with different backgrounds, perspectives and expertise?
Soru 5
Which risk identification technique lists factors that have a definite impact on the project by creating a simple matrix?
Soru 6
There are seven different tools and techniques that you can use to perform qualitative risk analysis. Which of the following cannot be listed among them?
Soru 7
What is the process of numerically analyzing the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives?
Soru 8
Which quantitative risk analysis is an analysis technique used to determine which
variables in a system affect the system more?
variables in a system affect the system more?
Soru 9
With which of the risk avoiding strategy the risk does not disappear but shifts to the third party?
Soru 10
Which data analysis technique used for risk monitoring focuses on productrelated risks such as scope, functionality, and quality?