ULİ460U
DİPLOMATİK YAZIŞMA VE PROTOKOL
4. Ünite
Soru 1
Which of the followings is NOT one of the the Four M’s, which is a common framework for defining the resources available for a project?
Soru 2
Which of the followings are the advantages of successful resource management for a company?
Soru 3
Which of the followings is the first step of the resource management?
Soru 4
In which of the following techniques are activities broken into pieces and resource requirements estimated for these small pieces while estimating resources?
Soru 5
In which of the following steps are the resources required to complete all the activities with respect to the resource allocation step outputs summed?
Soru 6
What is the first step to be applied to level the resources after calculating the total resource hours needed for each activity in Resource Leveling?
Soru 7
Which of the followings is NOT one of the types of organization charts?
Soru 8
In RACI model, who does "R" refer to?
Soru 9
In which of the followings are the works described above done?
Soru 10
Which of the following resource management software tool does the things described above?
Soru 11
All of the following is one of the four "M"s of resource management, except...
Soru 12
I. Key resources
II. Secondary resources
III. General resources
Which of above is/are among the categories made depending on the importance of the resources?
Soru 13
All of the following is among "the four key steps of successful resource management process", except...
Soru 14
I. Avoids unexpected delays II. Builds transparency III. Causes fatigue Which one of the above is/are among the benefits of the successful resource management applications?
Soru 15
Which one of the following is the first step of resource management?
Soru 16
Which of the following is an advantage of the resource allocation?
Soru 17
I. Creating resource loading table
II. Determining activity late finish dates
III. Identifying resource overallocation
Which of above is/are among the steps which can be applied after calculating the total resource hours needed for each activity?
Soru 18
Which of the following is a type of organizational structure in which team members report more than one project manager?
Soru 19
A good staffing management plan consists of all of the following, except...
Soru 20
I. Microsoft Project
II. Hub Planner
III. QuarkXPress
Which of above is/are among the widely used resource management software options?