ULİ460U
DİPLOMATİK YAZIŞMA VE PROTOKOL
3. Ünite
Soru 1
"Projects were planned utilizing bar charts until around ________." Which of the following can complete the gap correctly?
Soru 2
What is the visual representation of the project’s content and goals in project scheduling?
Soru 3
I. network planning
II. network implementation
III. network control
IV. network scheduling
Which of the above are the stages of the fundamental network assessment of the project?
Soru 4
Which of the following process involves resource allocation and time-cost trade-offs in network analysis?
Soru 5
Which of the following is used to show one significant event?
Soru 6
Which of the following occurs when there is a prevalent predecessor for two or more operations?
Soru 7
Which of the following is a visual representation of a project’s activities and the preceding requirements for completing the project?
Soru 8
How many kinds of data are required to describe a project?
Soru 9
Which of the following is NOT one of the principles to adopt when creating an AOA network diagram?
Soru 10
Which of the following is NOT one of the differences between AOA ve AON?
Soru 11
Which of the following network component refers to an arrangement of precedence that determines the pattern of activities?
Soru 12
I. Time information
II. Presedence relationdhips
III. Activity relationships
IV. Restrictions
Which information above is required to describe a project?
Soru 13
Which information below is true about the comparison between AOA and AON?
Soru 14
Which of the following refers to activities that may have been carried out before, containing a considerable number of elements of chance?
Soru 15
Which of the symbols below represents the most likely time?
Soru 16
Which of the following information is FALSE about the steps of PERT?
Soru 17
I. Predictions provided by an experienced person
II. Estimates provided by the results of simulation scenarios
III. Customer requirements
Which strategy above can be used to determine the duration estimates necessary for PERT?
Soru 18
Which of the following is one of the constrains that arise in PERT?
Soru 19
Which of the following information is FALSE about PERT?
Soru 20
Which of the following information is FALSE about CPM?