ULİ460U
DİPLOMATİK YAZIŞMA VE PROTOKOL
3. Ünite
Soru 1
"... is the time phased processing of operations subject to precedence interactions, time constraints, and resource constraints in order to achieve particular goals."
Which of the following would best fill the blank space above?
Soru 2
Until when were projects planned utilizing bar charts?
Soru 3
I. CPM
II. PERT
III. Decision Tree
Which of above can be considered as techniques of network analysis for project scheduling?
Soru 4
All of the following are the stages of the fundamental network assessment of the project, except...
Soru 5
I. Node
II. Arrow
III. Activity
Which of above is among the components of the network?
Soru 6
"... occurs when there is a prevalent predecessor for two or more operations."
Which of the following would best fill the blank space above?
Soru 7
All of the statements below are true, except...
Soru 8
"The estimation equation for mean is distributed in ... standard deviations in PERT."
Which of the following would best fill the blank above?
Soru 9
I. Compute the variance of each activity by using formula
II. Calculate the expected project duration
III. Calculate the expected value of each activity
Which of above is among the major steps of PERT?
Soru 10
All of the following statements about PERT is true, except...
Soru 11
"Project scheduling ______" Which of the following most appropriately completes the sentence above?
Soru 12
Which of the following is not one of the components of the network?
Soru 13
Which of the following is a data required to describe a project?
Soru 14
Which of the following is not one of the principles in adopting when creating an Activity on Arrow network diagram?
Soru 15
Which of the following is true about "Activity on Arrow (AOA)" and "Activity on NodeAON)"?
Soru 16
Which of the following is not one type of project that the Program Evaluation and Review Technique and Critical Path Method can be applied to?
Soru 17
Which of the following is the first step in PERT analysis?
Soru 18
Which of the following is not one of the approaches used to determine the duration estimates for PERT?
Soru 19
Which of the following statement is false about the "advantages and limitations of PERT"?
Soru 20
Which of the following statement is true about "CPM"?