Soru 1
Which of the following is wrong according to the project definition content?
Soru 2
............................. is a non-simple, non-repetitive, one-time effort limited by budget, schedule and performance specifications designed to meet customer needs
According to the definition, which of the following should come to the dotted point?
Soru 3
Which of the following is not one of the project characteristics?
Soru 4
Which of the following is wrong when we compare project and ordinary work?
Soru 5
Which of the following is wrong according to difference of projects and ordinary work?
Soru 6
............................. definition is the process of developing a detailed description of the project and product.
Which of the following should come to the dotted point according to the continuation of the sentence?
Soru 7
Project scope is the keystone engaging all elements of a project plan. To guarantee that scope definition is complete,We can use checklist.Which of the following is not included in this checklist?
Soru 8
To draw an AON project network, which of the following is not one of the general rules to follow?
Soru 9
There are some terms in the project management that allow project workers and managers to interact with each other easily.Which of following is not one of them ?
Soru 10
....................A sequence of connected, dependent activities.
According to Constructing a Project Network Which of the following should come to the dotted spot?
Soru 11
Which of the followings are a part of the project definition?
Soru 12
Which of the following is the most distinctive feature for project when comparing it with an ordinary work?
Soru 13
There are three phases of Scope Management. Which of the following is the phase where the objectives and goals of the project are defined, tasks and resources are allocated, and budget & time constraints are established, and lastly the limitations of the project are identified?
Soru 14
Project scope is the keystone engaging all elements of a project plan. To guarantee that scope definition is complete, there is a checklist. Which of the following is the "significant point or event in the project" from these checklist?
Soru 15
Which of the following defines the short-duration tasks that have a definite start and stop point, consume resources, and represent cost?
Soru 16
Which of the followings present the obeys about the drawing an activity-on-node project network?
Soru 17
There are some terms in the project management that allow project workers and managers to interact with each other easily. Which of the following presents the activity has more than one activity immediately following it?
Soru 18
Which of the following is the term that defines one begins with the last project activity/ies and goes along the other sequential activity/ies through the network through the first activity/ies?
Soru 19
Which of the following behaves as a link, but it is not a “real” activity, so it does not have time duration?
Soru 20
Which of the following is the maximum allowable delay that can occur for noncritical activities?