Resource Management

4. Ünite 21 Soru
S

Which one of the following is not one of the benefits of successful resource management for a company?

  1. Avoiding unexpected delays
  2. Preventing overloads
  3. Building transparency
  4. Lacking a safety net
  5. Measuring efficiency

D. Lacking a safety net

S

What is the most common framework that includes the four M's to define the resources available for a project?

Money, material, machine and manpower are the Four M’s, which is a common framework for defining the resources available for a project.

S

What is the resource management according to APM? 

According to the APM (Association for Project Management) Body of Knowledge, which is the largest professional body of its kind in Europe, the resource management is ‘the acquisition and deployment of internal and external resources required to deliver the project, programme or portfolio’ (Management, 2012).

S

What are the benefits of successful resource management for a company?

Hansen (2018) and Rius (2019) summarize the benefits of successful resource management for a company as follows:

  • Avoids unexpected delays: By developing resource management plans, necessary resources can be predicted, and the unexpected delays may be avoided.
  • Prevents overloads and fatigue: Effective resource management allows us to prevent overloads of resources (fatigue for humans) and bottlenecks or roadblocks by using resource allocation, aggregation and leveling techniques.
  • Builds transparency: Resource management provides transparent information about the status and workloads of resources and builds transparency for all the shareholders of the project.
  • Measures efficiency: It allows us to measure the efficiency of resources and enable us to work on multi-project environment. It also helps us to calculate return on investment (ROI) ratio easily.
  • Provides a safety net and projection: Resource management lets us know that we did the best with the available resources in hand and it offers the future projection for the upcoming projects.
S

What is the best thing to do in order to get optimal performance from the resources?

In order to get optimal performance from the resources, schedule the most valuable resources (i.e. key resources) which are the most critical and problematic resources first. This will also help you organize other resources easier.

S
What is the most important resource of the companies?

Remember, humans are also resources, and as it is always said, human resource is the most important resource of the companies.

S

What are the steps of resource management?

Steps of Resource Management

Estimating resource

Resource allocation

Resource aggregations

Resource leveling

Resource forecasting

S

How many techniques and tools are there in estimating resources?

Estimating Resources

The first step of resource management is the estimating of resources.

According to Bpayne and Adrienne Watt (2014), there are five techniques and tools to estimate the resources for each activity in the project schedule.

  • Expert judgment: One of the useful techniques to estimate the resources for each activity is to gather experts, who have done a similar project before and who knows which resources may be needed for this kind of a project.
  • Published estimating data: Another good way of estimating resources is to look for published data of other projects such as articles, books, magazines, etc. This technique is widely used among the project managers to benchmark and compare the performance of their project and to estimate the future requirement of resources.
  • Project management software: As already mentioned above, an intelligent resource management software, which lets you analyze the “what-if” scenarios, can be very useful to estimate the resources required for future projects. Details about resource management software are provided in the following subsections.
  • Bottom-up estimating: In this technique, activities are broken into pieces and resource requirements are estimated for these small pieces. These estimates are summed up to find the total estimate of the project. Even though it provides very accurate estimates, it is very time consuming since each activity in the project schedule must be assessed carefully. Therefore, if the project manager divides project into smaller pieces, it brings more accuracy, but at the same time more cost to the technique.
  • Alternative analysis: There may be more than one way of accomplishing an activity in terms of the number and the kind of resources. Therefore, alternative analysis must be developed to decide which alternative is the most proper one for the project (Watt, & Watt, 2014).
S

What is the name of the step in which resources are assigned to the specific activities in the project schedule?

Resource Allocating

The resource allocation is the second step of the resource management. In this step, resources, which are defined in the first step, are assigned to the specific activities in the project schedule.

S

What are the challenges that a project manager must be aware of in project allocation?

Even though it has several advantages, resource allocation has several challenges that a project manager must be aware of. In their website, Paweł Hałabuda (2019) summarizes these challenges as follows:

  • Client Changes: Any changes in the scope, the due date or the budget can easily affect the current resource allocations. Hence, a good project manager must always be ready to adjust the resources with respect to the possible changes.
  • Availability of Resources: Having multiple projects that share the same resources, broken machines, or sick workers force a project manager to monitor the resources all the time since availability of resources can suddenly change.
  • Activity Predecessors: A project manager must pay great attention to the activity predecessors while allocating the resources. In most cases, there exist some activities in the project which cannot be started before some other activities are completed. In such cases, the resources to be used in these activities do not need to be prepared in advance.
  • Changes in Priorities: Changes in the priorities among the projects is a common problem for a company if multiple projects run at the same time. In this situation, the resources, which a project manager has already allocated, may be needed by the other project that has a high priority for the company (Hałabuda, 2019).
S

When is resource aggregation step very vital?

This step is very vital when the same resources are shared among different projects in a multi-project environment.

S

What is the aim in resource leveling?

In resource leveling, the aim is to solve the resource conflicts by shifting (mostly delaying) the dates of the tasks.

S

What are the top-five tips for resource forecasting in project management?

Top-five tips for resource forecasting in project management are as follows:

  • Skills needed for the project must be thoroughly understood.
  • Strengths and weaknesses of the project team members must be clarified.
  • Investigate the recent projects to determine the usage (over or underutilized) of the resources and use these data to predict the future resource requirements.
  • Assign the right resources to right activity in the project plan.
  • Statistics about the resources such as employee turnover rate, recruitment trends, and return on investment must be kept under control (Daugherty, 2019).
S

What is the main purpose of project human resources management?

In project human resources management, the main purpose is to guarantee that there are enough human resources, with the right skills, knowledge, and experience to complete the project successfully.

S

What are the four types of organization charts?

There are mainly four types of organization charts: functional organization, projectized organization, matrix organization, and composite organization.

S

What is the name of the most widely used model in the literature to describe the responsibilities of the people involved in a project?

Even though there are different models to describe the responsibilities, RACI model is the most widely used model in the literature, which is derived from the key responsibilities: Responsible, Accountable, Consulted, and Informed.

S

Which parts does a good staffing management plan consist of?

A good staffing management plan consists of introduction, staffing requirements, staff assignments, and training, rewards and reassignment parts.

S

What are some characteristics of resource management software?

Resource management software can provide a clear view of resource usage and prevent resource allocation conflicts. It also allows us to follow who is working on which project, when the activity started, and how long it will take. Furthermore, it provides some real-time data analytics and historical and forecasted resource usages that give the project managers and other stakeholders valuable insights to trace the progress of the project over time.

S

What is another name for resource management software?

Resource management software is the best assistant of the project manager. In literature, it is sometimes referred as resource capacity planning software.

S

What kind of functions can a company realize by incorporating an effective resource management software?

  • determine the actual demand and capacity,
  • prioritize project requests for both project manager and clients,
  • obtain actual resource availability,
  • assign the necessary resources on the correct work and at the right time,
  • find out which skills and roles are needed and provide labor hiring plans,
  • establish more effective communication between team members, project manager, and other stakeholders,
  • predict possible problem areas and provide valuable information for risk management plans,
  • implement different objective methods for prioritizing the activities and analyze the output of what-if scenarios,
  • prepare customizable, summarized and automated reports to give each stakeholder the insight they require (Townsend, 2019).
S

What kind of questions are asked in price-performance ratio criteria?

Price-performance ratio: Are there any buying options for different requirements? When compared with the similar software, how appropriate is the price? Does the price cover possible system upgrades? Is there a time-based usage fee, such as an annual usage fee or annual licensing fee?