Which of the following allows the presentation of a diagram representing the choices between at least two or more options?
Soru 2
Which of the following defines to shift the risks to the third party while the risk does not disappear?
Soru 3
Which of the following includes reducing the likelihood of risk occurring or the effect of damage?
Soru 4
Which of the following are a part of the monitoring risk? Monitoring the implementation of agreed-upon risk response plans, Tracking identified risks, Identifying and analyzing new risks, Evaluating risk process effectiveness throughout the project, Developing the risk standardization
Soru 5
Which of the following are true expressions about the risk monitoring?
Soru 6
What is an uncertain event or condition that, if it occurs, has a positive or negative effect on one or
more project objectives?
more project objectives?
Soru 7
What type of risks is defined as specific events or conditions that may affect project objectives?
Soru 8
Which of the following is the process of defining how to conduct risk management activities for a project?
Soru 9
Which of the following is done to to obtain a comprehensive list of individual project risks and sources of overall project risk while identifying risks?
Soru 10
Which of the following is used used to identify important issues to consider and ensure that they are not
omitted?
omitted?
Soru 11
Which of the following has all of the inputs of Qualitative Risk Analysis completely?
Soru 12
Which of the following is not among the tools that can be used to perform qualitative risk analysis?
Soru 13
Which of the following analysis is the process of numerically analyzing the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives?
Soru 14
Which of the following analysis is an analysis technique used to determine which variables in a system affect the system more?
Soru 15
Which of the following strategy for positive risks or opportunities is aimed to find the best way to take advantage of the opportunity by eliminating the uncertainty in the project?
Soru 16
Which of the followings is included in the project management plan?
Soru 17
Which of the following techniques lists factors that have a definite impact on the project by examining the Strength, Weaknesses, Opportunities, and Threats?
Soru 18
Which of the followings is NOT one of the qualitative risk analysis tools and techniques?
Soru 19
In which quantitative risk analysis technique is it determined what variables in a system affect the system more?
Soru 20
When agreeing with a supplier, selecting a supplier who has already worked with our company can reduce many risks. This is an example to a _________.